High Court Judge Justice Raulston Glasgow has delivered a judgment in a case that could have far-reaching implications for the conduct of Environmental Impact Assessment (EIA) for development projects in Grenada.
The judge handed down his ruling in a case brought by Grenada Land Actors Inc against the government-controlled Planning and Development Authority (PDA) of Grenada.
The judge took issue with the EIA done by companies for some of the major projects on the island – Levera Development, Mt Hartman and La Sagesse as raised by Grenada Land Actors (GLA).
He also chided PDA for the manner in which it was handling its business on behalf of the state.
The case attracted a battery of lawyers Leslie Thomas K.C and former high court judge Rita Joseph-Olivetti for GLA. Sydney Bennett K.C, Aleya Williams and Caryn Adams appeared for PDA, John Carrington K.C, Sheila Harris, Anand Ramlogan SC, Gina Dyer Munro and Daniella Williams-Mitchell as well as husband and wife Darshan Ramdhani K.C, and Sabrita Khan-Ramdhani along with Sydni Walker for the other Interested Parties in the case.
As a public service, THE NEW TODAY reproduces in full the Justice Glasgow ruling that can have implications for major development projects on the island:-
[287] More pointedly, Lord Boyd eloquently reasoned that –
“Where an application for judicial review involves issues of environmental concern it is not necessary that the applicant demonstrates an expertise in the subject matter. All that is required is that they demonstrate some knowledge or concern for the subject. So an amateur ornithologist or bird watcher might raise a concern about the potential loss of a bird’s habitat; or a fisherman about the effect of a hydro – electric scheme on fish; or a local historian about the effect on an archaeological or historical site; or a local resident on the loss of a local beauty spot frequented by the local community…The Board is satisfied that the appellants have demonstrated a sufficient interest in the environmental issues… In particular, Mr. Mussington’s scientific background, his knowledge of the flora and fauna in the area, his status as a local resident, and his experience of conducting environmental assessments amply demonstrate a sufficient interest in the subject matter of the application for judicial review.”
The Board’s reasoning in Mussington is wholly applicableto the instant case. When the learning in Mussington is applied to this case, it is abundantly clear that GLA possesses the requisite standing to bring this claim. As the issues were distilled, it is clear that GLA have shown genuine concern in the environmental development of Grenada being exercised in a transparent, comprehensive and sustainable fashion.
[289] GLA has proven, through the complaints outlined in the evidence of Dr. Daniel, Mr. Joseph – Witzig, Ms. Ferguson and Mr. Joseph, that they have knowledge of the area, were resident in Grenada and have experience and were involved in conducting environmental assessments. In addressing Range’s complaint about GLA’s incorporation, having found that Dr Daniel and Mr. Joseph – Witzig had standing in their own individual capacity as persons concerned about the environment, I adopt the dicta in R v Leicestershire CC ex parte Blackfordby and Boothorpe Action Group Ltd –
“…The incorporation of a local action group ought not to be a bar to the bringing of an application for judicial review. Technically it may be said, the company does not have a relevant interest of its own; but in substance it represents the interests of local residents who, many of whom, do have a relevant interest. Incorporation has a number of advantages…It is true that another advantage is the avoidance of substantial personal liability of members for the costs of unsuccessful legal proceedings. But that should not preclude the use of a corporate vehicle, at least where incorporation is not for the sole purpose of escaping the direct impact of an adverse costs order …”
[290] The foregoing matters qualify them as having sufficient interest in the subject matter of the claim for judicial review, and I find that GLA does in fact have standing to bring the instant claim.
WHAT, IF ANY RELIEF, SHOULD BE GRANTED TO GLA.
[291] Having considered the matters in the round, and for the reasons stated above, I do not agree with much of GLA’s filed case. My reservations about the golf course at Levera and the lagoon at La Sagesse have been outlined above. This means that GLA has been only partially successful in its concerns about PADA’s determination of the applications for planning permission for the 3 projects.
[292] GLA has sought extensive remedies in this claim, and for the areas in which GLA has succeeded, this court has the discretion to make the declarations and orders requested by GLA. In exercising its discretion however, I am mindful of the concerns raised by PADA and the Interested Parties about why GLA’s relief ought not to be granted, principally due to GLA’s delay in bringing the claim. The issue of delay will therefore be considered at this stage.
DELAY
Range’s delay arguments
[293] Range first raised the issue of the delay in this claim in its application to be added as a party to the claim and again in its application to strike out GLA’s claim. In prior rulings in this matter, this court indicated that the issue of delay could be addressed at the substantive hearing of the matter. In both pre-trial and post-trial submissions, Range relied on rule 56.4 of CPR 2023, Bass, Roland Browne v AG and PSC199 and R v Lichfield District Council and Christopher J.N. Williams ex parte Securities Limitedto make the point that GLA’s delay is relevant at 2 stages – first as a bar as an application for leave, and secondarily as a discretionary bar to the granting of any relief.
[294] Range also lamented that their development has been completed, employing hundreds of Grenadians, and it would not be in the interests of good administration to grant any of the reliefs sought by GLA about Range’s planning permission. Range makes the point that Dr. Daniel began to engage with Range from March 2020, and between August 2020 and 29th March 2021, there were several communications and documentation passed between the parties. Range further indicates that it was not until January 2021 that GLA was incorporated and another 3 months passed until GLA sought leave for judicial review on 26th March 2021.
Heng Sheng’s delay arguments
[295] Heng Sheng addressed the issue of delay in its closing submissions by providing a helpful chronology of the timeline of Heng Sheng’s application for approval in principle in December 2019 and the approval for the construction of temporary workers housing in June 2020. Heng Sheng points out that from Mr. Joseph – Witzig’s evidence, he became aware of the Levera development in August 2020, members of GLA attended a meeting about the Levera development in September 2020 and GIS published a newsletter indicating that Levera’s EIA was still in progress in September 2020.
[296] Heng Sheng submits that GLA’s evidence does not give a clear reason why it took 7 months from GLA’s awareness of the development to the filing of the application for leave. Heng Sheng further submits that GLA never sought an injunction to stop the progress of the works and that it instead spent some time on a petition to put political pressure on PADA, as an alternative to seeking judicial review. Heng Sheng relies on R (Thorton Hall Hotel Ltd) v Wirral MBC as outlining the principles that should guide the court when considering delay –
“When a grant of planning permission is challenged by a claim for judicial review, the importance of the claimant acting promptly is accentuated. The claimant must proceed with the greatest possible celerity; where third parties have had a fair opportunity to become aware of, and object to, a proposed development… objectors aggrieved by the grant of planning permission must reasonably be expected to move swiftly to challenge its lawfulness before the court…Developers are generally entitled to rely on a grant of planning permission as valid and lawful unless a court has decided otherwise…the concept of detriment to good administration is not tightly defined, but will generally embrace the length of the delay in bringing the challenge, the effect of the impugned decision before the claim was issued and the likely consequences of its being re-opened.”
Hartman’s take on the delay point
[297] Hartman submits that GLA failed to act with the requisite promptness, because GLA did not file its claim until almost 18 months after the decision and almost 8 months after GLA alleges it became aware of the decision. Hartman also points out that GLA did not seek injunctive relief, and as a result, the Hartman development has substantially progressed. Hartman also invited the court to consider the meaning of “undue” or “unreasonable” delay in the jurisprudence on judicial review claims in the Commonwealth Caribbean, and submits that the general approach is summarized in the Fordham’s Judicial Review Handbook as –
“A claimant has a duty to act promptly, not a right to wait for up to three months. Some contexts are recognized as calling for special, sometimes the utmost, promptness. The clock starts when the grounds first arise and does not stop until the claim is lodged…Care is always needed in letting time lapse”.
[298] Hartman also relied on R v Cotswold District Council ex parte Barrington Parish Council and submits that to grant GLA’s relief now would prejudice the rights of the company as an innocent third party and amount to a detriment to good administration. Hartman continues that this is not a case of delay simpliciter and Hartman is not barred from raising the issue of delay, as the Court of Appeal permitted the revisiting of the issue of the delay at the substantive hearing.
GLA’s response to the delay issue
[299] GLA’s rejoinder is that the timing of the claim must be examined against the backdrop of PADA’s failure to provide the Grenadian public with information about the developments. The foregoing, GLA claims, is compounded by the register containing sparse and limited information. GLA also rejects the suggestion that there was unreasonable delay, pointing out that this court granted leave to apply for judicial review with full knowledge of the time that had elapsed since the decisions under challenge and the issuance of the claim. GLA suggests, in reliance on Bass, that the court should adopt the learning in R v Lichfield DC ex parte Lichfield Securities Ltdthat the issue of delay should only be revisited where –
“(i) if the judge hearing the initial hearing has expressly so indicated; (ii) if new and relevant material is introduced at the substantive hearing; (iii) if exceptionally, the issues as they have developed at the full hearing put a different aspect on the question of promptness; (iv) if the first judge has plainly overlooked some relevant matter or otherwise reached a decision per incuriam.”
[300] GLA argues that none of the above criteria have been satisfied. GLA further laments that GLA only effectively became aware of the status of the developments after disclosure was ordered. GLA’s position is that the decision making done by PADA was done behind closed doors, and asked the court to consider R (Macrae) v Herefordshire District Council, where the court reasoned –
“Whether an application for permission to apply for judicial review is made promptly will depend upon all the circumstances. One of those circumstances is the extent to which the alleged error of law in the decision is plain or whether the decision “leaves the claimant in the dark” as to the basis on which it was taken. In the latter case it would normally be reasonable for the claimant to seek to ascertain, so far as he reasonably can, what was the basis for the decision before he resorts to litigation.”
[301] GLA therefore asks the court to find that there has been no unreasonable delay in bringing this claim and that the reliance on the advanced stages of development and the detriment to be caused to good administration as argued by the Interested Parties as misconceived. GLA avers that it has consistently sought to progress the matter and avoid delays, pointing out that most of the delay during the proceedings was caused by PADA and the Interested Parties’ “tactical decision” to apply to strike out the claim, and appeal the refusal of those applications, rather than proceeding to an early trial.
My take on delay in this case
[302] Rule 56.4 of CPR 2023 deals pointedly with the issue of delay –
“(1) In addition to any time limit imposed by any enactment, the judge may refuse to grant relief in any case in which the judge considers that there has been unreasonable delay before making the application.
(2) When considering whether to refuse to grant relief because of delay the judge must consider whether the granting of relief would be likely to –
(a) be detrimental to good administration; or
(b) cause substantial hardship to or substantially prejudice the rights of any person.”
[303] The learning on delay in Fishermen and Friends of the Sea v The Environment Management Authority and BP Trinidad and Tobago LLC as reinforced in Devant Maharaj v National Energy Corporation of Trinidad and Tobago found –
“41. The allocation of issues of delay and extension of time, on the one hand, and prejudice and detriment to good administration on the other, to discrete hearings may have lent some support to the notion that extension of time is a threshold issue and that issues of prejudice or detriment do not arise at that stage. However, for the reasons given at paras 27 and 28, above, Caswell provides no justification for the claimed insulation of these issues from each other. Furthermore, civil procedure has developed considerably in England and Wales since 1990. Nowadays the pre-action letter of response allows a respondent or interested party to draw attention to the possibility of any prejudice or detriment. Compliance with pre-action protocols and the Civil Procedure Rules should ensure that in most cases issues of prejudice or detriment to good administration are identified at the outset. Where such issues are raised by a defendant in the context of delay, it will be open to the judge to adjourn the question of leave to an inter partes hearing or to order “a rolled-up hearing”, at which leave will be considered, followed immediately by the substantive application, if leave is granted. (Greenpeace II, for example, was a rolled-up hearing.) In either case, full consideration can be given to issues of extension of time, prejudice and detriment, on the basis of evidence filed by the parties. In any event, even if leave is granted without full consideration of issues of prejudice and detriment resulting from delay, these may still be a bar to relief at the substantive hearing…” (bold emphasis mine)
[304] The case law is settled that the court has the discretion to grant relief as is appropriate, based on the facts and circumstances of each individual case. The case law is well established that the grant of judicial review is discretionary and that it does not immediately follow that if an unlawful act is found that there is an unqualified right to any of the remedies claimed. One of the factors for the court’s consideration is the advanced stage of development of the projects, and for present purposes, this court notes that the Range project is now fully operational as the Six Senses Hotel.
[305] However, as found by the Board in Mussington,
“The fact that the airstrip is complete does not render the question moot. If, as a result of any subsequent procedure, a court finds that the DCA acted outwith its power then it will be for the court to determine what remedy, if any, should be afforded to the appellants. The remedies potentially available would include an order requiring the land to be restored to its original state.” (bold emphasis mine)
[306] While accepting that the public register was not adequately maintained and accessible as required by the Act, the evidence suggests that GLA had sufficient engagement with the 3 developments to do 3 comprehensive reviews of the EIAs. There was also some delay in GLA’s part in taking the initiative to commence this claim. Taking the matter in the round, GLA could have acted with more alacrity to bring their claim after becoming aware of the developments concerned and not wait almost an entire year to commence proceedings.
[307] However, while criticism may be thrown at GLA for its failure in this regard, I do not believe that it ought to be refused relief on the issue of the golf course and the lagoon on this basis, especially when considering the phased approach to development undertaken by the Interested Parties. The Interested Parties have led evidence that the projects have advanced, but there is no evidence that the golf course at Levera or the lagoon at La Sagesse have commenced development in any substantial way.
OVERALL FINDINGS
[308] In the circumstances of this case, and considering the fact for all three projects, there has been substantial progression occurring and finding only minimal challenges with respect to the golf course and lagoon, I will only make orders with respect to those 2 decisions. I make this determination after much deliberation on the background circumstances.
[309] I do not find that, except with regards to the Golf Course and the Lagoon, that PADA acted wholly unreasonably by arriving at the decisions which it did. In almost all of the projects, there was substantial information to inform planning judgments made by the Authority. This finding is made after considering not only the EIA for the projects, but information that it had gained from previous EIAs and studies, its own knowledge of local conditions gained from site inspections and reports from different government agencies.
[310] While PADA’s exercise of its discretion was not perfect, it must be recalled again, that the scrutiny required on exercises of this sort is not a scientific dissection of the merits of the planning authority’s functions. As tempting at it may appear to prefer a more or less rigorous approach to planning decisions and to cavil about a planning decision to grant permission to develop land, the law demands nothing more than an examination as to whether what was done was lawful, procedurally fair and/or not so outrageous as to amount to a failure to make a decision at all. This is not the case with respect to these 3 projects. However, as I have found, there ought to have been further scrutiny and requests for further information on the golf course at the Levera site and the lagoon at the La Sagesse site.
[311] Some of GLA lamentations were not found to be insubstantial or trivial, as the need for adequate protection and preservation of the natural environmental are not matters to be taken lightly or minimized and the public register ought to be properly maintained as required by statute. However, none of what was presented leads me to conclude that PADA acted unlawfully or unreasonably in granting the planning permissions in question. As appeared throughout this matter, PADA had a plethora of material before it and considered what it ought to consider and acted lawfully and reasonably in so doing. At the end of the day, it is for the policymakers and the planning authority to determine what is necessary for sustainable development of the resources of the State, even where members of the society may think that limited or no development ought to occur in certain areas.
[312] The courts are only there to step in when what is done is in breach of the law and procedure or is so blatantly unreasonable or irrational. A graphic example in the case is that of the Ramsar site boundaries. GLA complains that the decision would reduce the boundaries of the Ramsar site. PADA rejoins that the State has surveyed the site and delineated the boundaries. As such, PADA asserts, the boundaries claimed by GLA are incorrect. PADA has also assessed that the buffer between the development and the Ramsar boundaries are quite adequate for sustainable development purposes.
[313] PADA has also testified before this court that the developer was asked to reduce and has so reduced the size of the project site to ensure a sufficient buffer between the development and the Ramsar site. These are policy and planning considerations and the State itself is permitted to build within the Ramsar site, so long as it does in a sustainable manner. As stated by Sullivan J in R (Newsmith Stainless) v Secretary of State for the Environment, Transport and the Regions courts must be astute to ensure that such challenges are not used as a cloak for what is in truth a return to the arguments on the planning merits. I find that GLA has attempted in many respects to do just what the court is enjoined to guard against, that is, attacking planning decisions on their merits, because they may be unhappy about policy decisions being made.
[314] I am also reminded that judicial review claims are to be heard and dispensed with expedition. This is due to the need for finality and certainty about planning decisions, as finality and certainty are also especially important from the developer’s standpoint, since the latter may lose significant financial input by inordinate delay. I will confess that a considerable part of the delay in rendering this decision lay in the sometimes pedantic manner in which this case was presented by some of the participants.
[315] Considering all the foregoing, I will order that the golf and lagoon approvals be set aside as requested by GLA. I will also direct PADA to reconsider the applications for the golf course and lagoon in light of the observations that I have made above. I will also grant the remedies sought with respect to the public register. All of GLA’s other claims for relief are accordingly refused, having been found to be unmeritorious.
COSTS
[316] Based on the foregoing, GLA has only been partially successful in its claim against PADA. Considering the discretion of the court on costs, and in the circumstances, I award costs to GLA in the sum of $5,000.00, payable by PADA within 28 days of this decision. I will not award costs against GLA for the parts of its claim that failed.
[317] I see no reason to depart from the general rule on costs in these matters as stipulated in CPR 56.11(6) 2023, which circumscribes the court’s discretion to award costs against an unsuccessful applicant. The rule would only allow costs against an unsuccessful applicant in administrative claims where the court finds that “the applicant has acted unreasonably in making the application or in the conduct of the application.” There is nothing on this claim to suggest to me that GLA, while incorrect in its assessment of the propriety of PADA’s actions, has acted with anything but genuine, but somewhat over exuberant, concern about the environment and land development in Grenada. Although addressing rules of court in Trinidad and Tobago, commendable and helpful discourse on the development and rationale on the procedural rules on costs generally and more particularly in judicial review claims can be found in the Trinidad and Tobago consolidated Court of Appeal’s decision of Judicial and Legal Services Commission and Her Worship Magistrate Sarah Da Silva.
CONCLUSION
[318] With caution to PADA that it runs the risk of having its decisions challenged or set aside if they continue to show wanton disregard for their public duty to keep a proper register and to allow access to persons as prescribed by law, they have been partially successful in defending this claim. The disclosures made in these proceedings do not sanitize PADA’s failures to keep the register maintained in the manner required by the Act, with the consequences of such failings being protracted legal challenges, the incurring of tremendous costs and much anxiety.
[319] GLA is also reminded that environmental control is an iterative process, which does not end with the approval of an EIA and that while debate on development is wholesome and to be always encouraged, the ultimate arbiters on the question is the policy maker. Our democratic structures are framed along these lines. Thus, while we may disagree with the policymakers about their approach to development issues or even their decisions, it is their remit and their remit alone to make such decisions, so long as they follow the prescribed law and applicable procedures written or otherwise. As observed by Lord Legatt in R (On the application of Finch on behalf of the Weald Action Group) v Surrey County Council and others
“The legislation does not prevent the competent authority from giving development consent for projects which will cause significant harm to the environment. But it aims to ensure that, if such consent is given, it is given with full knowledge of the environmental cost.”
[320] In light of the foregoing discourse, it is ordered that:
1) A declaration is granted that PADA has failed in its public duty to keep a publicly accessible register in accordance with section 69 of the Act;
2) An order of mandamus is made directing PADA to update the existing public register in respect of the 3 projects and thereafter to maintain the register in accordance with section 69 of the Act and the common law;
3) An order of mandamus is made directing PADA to produce to GLA in respect of the La Sagesse development, the Levera development and the Mt. Hartman development, conditional upon payment of the prescribed fees, the planning applications, all plans, information and material as defined in section 69 of the Act;
4) A declaration is granted that the decision of 25th May 2022 to grant planning permission for the golf course at Levera in the parish of Saint Patrick was irrational because the EIA done by Niles and Associates dated March 2021 was so inadequate in addressing the environmental impact of the golf course that no reasonable authority could have relied upon it to grant planning permission;
5) An order of certiorari is made quashing the decision made on 25th May 2022 by PADA to grant permission for the golf course at Levera;
6) An order of mandamus is made directing PADA to reconsider Application No. 19232 for planning permission with respect to the golf course at the Levera development;
7) A declaration is granted that the decision dated 27th January 2021 to grant planning permission for Range to develop the Lagoon at La Sagesse was irrational in that the EIA by Jeco Caribbean dated June 2019 was so inadequate with respect to the lagoon that no reasonable authority could have relied upon it to grant planning permission;
8) An order of certiorari is made quashing the decision made on 27th January 2021 by PADA to grant permission for the lagoon at La Sagesse;
9) An order of mandamus is made directing PADA to reconsider Application No. 18397 for planning permission with respect to the lagoon at the La Sagesse development;
10) PADA shall pay costs in the sum of $5, 000.00 to GLA within 28 days of this decision;
[321] I also wish to take this opportunity to thank all counsel for their fulsome and engaging written submissions and their immense patience in awaiting the ruling in this claim.
Raulston L.A. Glasgow
High Court Judge
BY THE COURT