High Court Judge Justice Raulston Glasgow has delivered a judgment in a case that could have far-reaching implications for the conduct of Environmental Impact Assessment (EIA) for development projects in Grenada.
The judge handed down his ruling in a case brought by Grenada Land Actors Inc against the government-controlled Planning and Development Authority (PDA) of Grenada.
The judge took issue with the EIA done by companies for some of the major projects on the island – Levera Development, Mt Hartman and La Sagesse as raised by Grenada Land Actors (GLA).
He also chided PDA for the manner in which it was handling its business on behalf of the state.
The case attracted a battery of lawyers Leslie Thomas K.C and former high court judge Rita Joseph-Olivetti for GLA. Sydney Bennett K.C, Aleya Williams and Caryn Adams appeared for PDA, John Carrington K.C, Sheila Harris, Anand Ramlogan SC, Gina Dyer Munro and Daniella Williams-Mitchell as well as husband and wife Darshan Ramdhani K.C, and Sabrita Khan-Ramdhani along with Sydni Walker for the other Interested Parties in the case.
As a public service, THE NEW TODAY reproduces in full the Justice Glasgow ruling that can have implications for major development projects on the island:-
[31] Mr. Joseph – Witzig argued that none of the approvals complied with the law, and highlighted that none of the interested parties, outside of Range, disclosed all relevant documents to the court, such as its title documents, during the pendency of the claim. He also asserted that GLA conducted in-depth reviews of the documents relied on, including the EIAs, and found them to be wholly inadequate, rendering any permission grounded on the EIAs irrational, unreasonable and unlawful.
32] Mr. Joseph – Witzig further indicated that PADA’s Mr. Frederick made several references to the EIA Committee, but this committee appeared not to be established in strict accordance with the Act, and was not active at the time when the developments were approved. Mr. Joseph – Witzig also pointed out that there was no proper documentary evidence supporting the approvals before the court, as PADA’s disclosures were void of any agendas, minutes or resolutions about its decisions to show what PADA considered prior to granting approval and its reasons for doing so.
Sandra Ferguson’s Evidence
[33] Ms. Ferguson is a development worker. She stated that she wrote to the head of PADA on 23rd November 2019 about 2 coastal tourism projects in True Blue and Grand Anse. In that letter, Ms. Ferguson recalled that she raised several concerns and requested information on when public consultations as part of the EIAs had been conducted. She also requested sight of the EIAs and contended that public consultations were integral to the EIA process.
[34] The letter was copied to the Chairman and other members of PADA, and to the Director of Environment, Ministry of Climate Resilience. This letter received no response. Ms. Ferguson then wrote to the Chairman of PADA, Mr. Frederick on 27th December 2019, renewing her request for sight of the reports on the EIAs for the 2 developments. This letter also received no response.
[35] Ms. Ferguson then wrote to the new Chairman of PADA, enclosing copies of her unanswered letters. She recalled that Mr. Frederick responded by letter of 27th January 2020 giving basic information about the developments, but did not address the request for EIAs or public consultation. Mr. Frederick also advised her that the necessary due diligence was done in the review process prior to the approval of the applications. This response caused Ms. Ferguson by letter of 27th February 2020, to renew her request for access to the EIA reports for the developments.
[36] Ms. Ferguson also deposed that on 18th March 2020, she visited PADA’s Physical Planning Unit’s office to request access to the EIA reports. She recalled that Mr. Frederick gave her a short meeting, and informed her that he did not have the authority to give her access to the EIA reports and asked her to point out the section in the Act which permitted her such access. Ms. Ferguson further deposed that she was taken aback by his response, as she expected that he would be acquainted with the Act and would advise her of the section which denied the public access to the EIA reports. Ms. Ferguson pleads that the EIA reports are public documents and to date, she had not been afforded the sight of several EIA reports which she had requested.
Reginald Joseph’s Evidence
[37] Mr. Joseph is a freelance photographer and videographer, who worked with various media entities in Grenada. He deposed that he was instructed by GAEA to take pictures to document the La Sagesse coastline in 2019. He was paid by GAEA for his work. He exhibited pictures which he indicated were taken of the La Sagesse Pond by a drone before development started, and pictures after the development started on 29th July 2020. He deposed that GLA requested that he take pictures to document the changes at Mt. Hartman, and exhibited pictures of these aerial photographs, which he explained were taken over several months in 2020 and 2021.
PADA’s RESPONSE
[38] PADA’s evidence was provided by Mr. Carlton Frederick, who filed 2 affidavits, and Ms. Nyasha Moore – Regis and Mr. Anthony Jeremiah, who each filed 1 affidavit. Witness summaries were also filed on behalf of Ms. Aria St. Louis and Mr. Trevor Thompson. PADA’s evidence is as summarized below.
Carlton Frederick’s Evidence
[39] Mr. Frederick is retired. He served as the former acting Chief Executive Officer of PADA from 8th January 2020 to July 2022. Prior to his appointment as CEO, he served as Chairman of PADA’s Board of Directors in 2019. He detailed the process for making an application to develop land, the supporting documentation required under the Act, and outlined the difference between approval in principle and final approval for development purposes. Mr. Frederick indicated that approval in principle does not equate to permission to commence development and that development can only occur after approval under the Act.
[40] Mr. Frederick recalled that during his tenure, when an application for approval was received, PADA would conduct site visits through site inspectors who prepared reports. These applications with supporting documents, including EIAs, would be sent to several governmental agencies for their review and comment. Mr. Frederick stated that an EIA may be required if the proposed development could significantly affect the environment.
[41] While the Act provides for regulations to be made for the appointment of an EIA Committee, Mr. Frederick points out that no such regulations exist. Notwithstanding the lack of regulations, an EIA Committee was formed with members including PADA’s Chief Planning Officer, the Senior Health Officer for the Ministry of Health, the Chief Technical Officer from the Ministry of Works & Infrastructure, the Senior Environmental Officer from the Department of Environment, the CEO of Lands, representatives from the Forestry and Fisheries Division and Mr. Frederick as Chairman. When an EIA is submitted to PADA, Mr. Frederick recounted that the EIA Committee would consider the draft.
[42] He recounted that the EIA Committee held several meetings with persons connected to or affected by the developments and conducted several site visits and consultations before decisions regarding applications were made by PADA. In making decisions, Mr. Frederick confirmed that the Committee first considered the EIAs submitted, and also, in this case, considered GLA’s reports and other public commentary. He discussed that all concerns were submitted to developers for relevant plan adjustments, and once these conditions were met, approval was given.
[43] Mr. Frederick indicated that he consulted the EIA Committee on the 3 developments by sending letters to the various public agencies in March 2020. Mr. Frederick recalled that these recommendations were then submitted to PADA’s Board of Directors, who made the final decision on whether an application was conditionally or wholly granted, refused, or whether further information was needed to make a decision. He stated that PADA also conducted periodical site visits to keep abreast of the developments, and the granting of approval was not the end of communications with developers.
[44] On the issue of the public register, Mr. Frederick indicated that the register is located at PADA’s office. He acknowledged that PADA received a letter on 14th September 2020 from GLA, requesting that copies of the notices for the grant of permission for the 3 developments be provided by 25th September 2020 – a mere 11 days. Mr. Frederick recalled that he informed GLA that the Unit was transitioning, and that it would be difficult to accommodate the request by the deadline. On 15th December 2020, Mr. Frederick wrote to GLA, indicating that their communication was passed to PADA’s legal representatives for legal advice.
[45] Following this legal advice, Mr. Frederick advised GLA that the Act permitted access to the documents following payment of the prescribed fees. Mr. Frederick further informed GLA that members of the public were allowed to view the register, but that PADA could not facilitate GLA’s demands for large volumes and copies of the documents in the time frame given. Mr. Frederick also admitted that the register was not always updated as mandated by the Act, due to severe staffing deficiencies within PADA.
[46] On the issue of public consultations, Mr. Frederick emphasized that PADA is not mandated by the Act to conduct public consultations at any stage of the development process. He however acknowledged that while public consultations were the preferred position, it was incumbent on the consultant conducting the EIA to do so. Mr. Frederick confirmed that the Interested Parties all held public consultations – Levera on 30th July 2020 and 6th April 2021, Hartman as early as 2011 and Range in August 2020.
[47] Mr. Frederick recalled that Levera applied for approval in principle, as the project was to be conducted in 3 phases – phase 1 (temporary staffing dorms), phase 2 (hotel rooms), and phase 3 (villas). He states that this approval in principle, further to the application dated 2nd June 2020, was conditionally granted and partially based on EIAs previously produced for large-scale developments in the same area in 2007 and 2015. He further recounted that these EIAs were used to obtain a general understanding of the whole development and its implications, but one of the conditions on granting the approval in principle required Levera to present an EIA before final approval was considered.
[48] Mr. Frederick recounted that a site inspection was conducted on 4th June 2020, and it was observed that works were done on the site arising from previous planning approval from a previous developer, but this work had minimal impact on the environment. He recalled that this previous developer commenced development but had not completed the permitted development before selling the property to Heng Sheng. Mr. Frederick deposed that PADA was satisfied that there were no serious environmental concerns, and that the EIA done for the previous developer was satisfactory and thus obviated the need for a new EIA.
[49] Mr. Frederick further deposed that by letter dated 30th June 2020, PADA restricted the clearing of the site to the already completed area, and required that further permissions be sought for any further land clearing. Mr. Frederick also recounted that permission was sought to construct a jetty so that material could be brought to the site in a more efficient manner. A revised EIA was submitted by Heng Sheng dated 20th January 2021, which took the jetty’s impact into account.
[50] During Mr. Frederick’s tenure with PADA, he liaised with Heng Sheng concerning the need for updated plans, EIAs and other general supporting documents before final approval could be granted, which Heng Sheng submitted. During Mr. Frederick’s tenure with PADA, he recalled that PADA never saw any interference with the RAMSAR site due to the Levera development.
[51] Mr. Frederick recalled that Heng Sheng sought to extend the golf course for which approval was given to the former developer. PADA requested that Heng Sheng resubmit the application, which was done. PADA reviewed the application as a separate development and used the EIA conducted by Mr. Niles for this purpose. After review and careful consideration, Mr. Frederick indicated that the proposed golf course was approved.
[52] The Hartman project was approved prior to Mr. Frederick’s tenure with PADA, as PADA’s records showed that the application for approval in principle and supporting documents were submitted by Grenada Resort Complex Limited and approved on 2nd September 2015 to develop 257 acres of land for a tourism resort. Mr. Frederick deposed that these approvals occurred before the Act commenced and the establishment of the EIA Committee.
[53] Mr. Frederick recalled that their records reflected further applications being made between 30th November 2015 and October 2019, based on an EIA submitted in 2015. Mr. Frederick recounted that PADA liaised with Hartman about concerns about the project, including requests for updated EIAs and master plans. By letter dated 20th December 2020, Mr. Frederick wrote to Hartman, granting conditional approval of the modified master plan on conditions of, among other things, Hartman presenting an updated EIA and a final application for development. Mr. Frederick indicated that Hartman presented an updated EIA to PADA in January 2021, and received approval in principle for additional development to commence development of a university campus and a hotel resort. He deposed that the updated EIA aided PADA with its assessment.
[54] Mr. Frederick recalled that PADA’s records showed that by letter dated 6th February 2019, Range submitted an application for approval in principle of a resort, including villas and individual accommodation units. Range then applied for permission to develop land in the La Sagesse area for the purpose of constructing a 78-room resort and provided extensive plans, drawings and other supporting documents. The clearing of land for construction was considered under Phase 1, and an EIA was submitted to PADA on 3rd July 2019.
[55] Mr. Frederick indicated that this application was conditionally approved on 29th January 2020, with some conditions being public consultation, reforestation efforts, and sediment preservation measures. Mr. Frederick deposed that in 2020, PADA was made aware that there had been a breach of the approval conditions. Members of the EIA Committee conducted site visits and met with the developers to discuss mitigation measures to address the breaches. He also deposed that Range sought further approval for the enhancement of an existing pond/lagoon, which was also conditionally granted, and PADA requested that Range install flooring barriers to regulate turbidity in the lagoon and employ other mitigation measures.
[56] PADA continued to monitor the implementation of the mitigation measures with Range, and Mr. Frederick reported that all measures were properly implemented thereafter. During Mr. Frederick’s tenure as CEO of PADA, several meetings were held with Range’s representatives to monitor the development’s progress. Range later applied for permission to clear land for phase 2 of its development. Mr. Frederick confirmed that PADA indicated by letter of 19th November 2020, that this request was deferred, subject to a site visit and inspection.
[57] Mr. Frederick concluded that PADA acted in compliance with and discharge of its duties under law, and nothing in the Act required, as a precondition to final approval, that PADA should first satisfy itself that a developer had title to the land, if a prospective purchaser had the owner’s approval to the proposed development. Mr. Frederick also found that the EIAs as submitted to be adequate.
Anthony Jeremiah’s Evidence
[58] Mr. Jeremiah served as the acting Chief Forestry Officer in the Ministry of Agricultural Lands and Forestry, and as a member of the EIA Committee for 1 year. He recalled that after EIAs were submitted to PADA, the EIA Committee usually got involved. At times though, he recalled, the Committee sometimes received requests for consultations prior to the submissions of EIAs, where feedback was requested on areas of concern to be addressed. Mr. Jeremiah indicated that PADA had guidelines for EIA preparation, which were sent to developers. His role was review of the EIA for forestry implications.
[59] Mr. Jeremiah recalled several interactions with consultants and developers for each project, and deposed that several EIAs were prepared for the Levera project over the years. He recalled that the consultant working on the Levera EIA wanted to know about the RAMSAR designation. Equally, when he attended public consultations on this issue in July 2020, feedback was provided to community stakeholders. Mr. Jeremiah recollected strong racist comments being expressed about the developers.
[60] Mr. Jeremiah deposed that the Levera developers did major revisions to their master plan by reducing the size of the development from 375 acres to 256 acres and the number of proposed villas by half. In his view, an adequate buffer zone for the protection of the RAMSAR site was established. He recounted that recommendations were made regarding lighting, guest control, visitation, access and furniture to mitigate the impacts on the nesting turtles and the environment.
[61] Mr. Jeremiah recalled that the Hartman area contained a National Park and Dove Sanctuary, which were established protected areas, and the development was a continuation of a prior development plan. In 2015, an application for planning permission was made and at that time, an EIA was submitted for review and concerns were raised. Site visits were conducted by Mr. Jeremiah and other consultants to observe whether the dove was present in the development area, and strong recommendations on the EIA were made.
[62] At the time of these recommendations, Mr. Jeremiah confirmed that they had strong commitment from the developers, but the project did not materialize. He deposed that they are currently engaging with the new developers to ensure that the earlier recommendations made are put in place. In November 2020, Mr. Jeremiah indicated that the developers submitted a new development plan, which appeared to incorporate more conservation measures and provided for less development, which eased up the environmental concerns.
[63] From Mr. Jeremiah’s viewpoint, the current activities were not impacting the dove sanctuary, and while there was some impact with the wetlands, it was in line with the approved updated development plan. He acknowledged that some mangroves were removed by Hartman and at that time, the final application and EIA had not been submitted, so the clearing should not have occurred. Mr. Jeremiah further deposed that when reviewing EIAs, a balance was always struck between monitoring the effects of development on the overall environment, and what could be removed or reintroduced in a sustainable manner according to the circumstances.
[64] On the La Sagesse development, Mr. Jeremiah recounted that planning permission was sought in September 2019 and an EIA submitted. On 12th March 2020, he submitted his comments on the EIA, highlighting several issues and making recommendations that further in-depth studies be undertaken on mangrove preservation. Mr. Jeremiah found that his concerns were not adequately addressed, as the developer cleared the coastal wetlands in a way that they could not be replanted without permission and in breach of their own EIA.
[65] Mr. Jeremiah pointed out that the EIA specifically provided for conservation measures for vegetation and trees. He deposed that PADA took immediate action to ensure that future development would include conservation of trees on a phased basis, and work was done such as identifying and tagging trees to be conserved. Mr. Jeremiah noted that the developer’s plans were complex and comprehensive, and the EIA Committee also recommended increased oversight on the project until another EIA was submitted. A subsequent EIA was submitted and in Mr. Jeremiah’s review, he felt that it was well researched and contained a succinct restoration plan for enhanced bird life. He therefore felt comfortable that the area would be restored.
Nyasha Moore – Regis’ Evidence
[66] Ms. Moore – Regis served as PADA’s Acting Chief Executive Officer. She deposed that the PADA may require that an EIA be carried out for any application for permission to develop land, if the proposed development could significantly affect the environment. The EIA guided PADA in deciding whether to grant planning permission for a project which is likely to have significant effect on the environment. She recalled that it is PADA’s practice once an EIA is submitted, to discuss, carefully consider and deliberate over it with the EIA Committee before planning permission is granted.
[67] Ms. Moore – Regis found that the Levera EIA conducted by Niles & Associates dated 4th March 2021 was satisfactorily and thoroughly conducted and that it caused PADA to carefully consider whether to grant permission for the development and on what terms. She found that the EIA substantially met the requirements of alerting the EIA Committee about the effect of the construction and operation on the environment and the development’s consequences to the community.
[68] Ms. Moore – Regis rejects GLA’s assertions that the decision to grant planning permission for the Levera development was irrational, or that the EIA was so inadequate that it could not be relied on. She also averred that PADA considered GLA’s Levera report prior to granting Levera’s final approval on 15th June 2023. Ms. Moore – Regis noted that the legislative framework did not mandate that PADA give reasons to members of the public for not implementing their suggestions or addressing their concerns. Ms. Moore – Regis concluded that PADA did not act unlawfully or in breach of any of its statutory or regulatory obligations in granting permission for any of the developments.
Aria St. Louis’ Witness Summary
[69] Ms. St. Louis served as the Head of the Environmental Division at the Ministry of Tourism, Civil Aviation, Climate Resilience and the Environment. She is an Environmental Specialist and has been employed with the Environmental Division for more than 10 years. When Hartman’s application for planning permission and EIAs were first submitted in 2015, she did not have sight of them, as she was on maternity leave. Thus, her first interaction with the project was after the renewed application for planning permission had been made and granted.
[70] The first meeting Ms. St. Louis attended as a member of PADA’s Board was in January 2020. As the Hartman project was viewed as a revised and not new project, the Board was of the view that a revised EIA was required. By letter dated 24th November 2020, she recounted that the developers of the project sought permission to modify the master plan for the project. PADA’s Board considered this proposal at its meeting of 22nd December 2020 and approved the modification to the master plan on 28th December 2020.
[71] The developers were still required to submit an EIA, which had to be approved before any works could occur on the project. She noted that a consultant was retained and stakeholder consultations were undertaken. Ms. St. Louis pointed out that normally, when an EIA is submitted for a project, it is reviewed by the EIA Committee. The EIA Committee then submits a report to PADA’s Board for consideration. When PADA’s Board received the report, she confirmed that it is considered and a determination is made on whether to grant approval with conditions.
[72] Ms. St. Louis was not present at PADA’s Board meeting of December 2019 when approval in principle was granted for the Levera site. One of the main concerns for this project was its proximity to the Ramsar site, as the Levera project had a long history, dating back to 2007. PADA made a visit to the site on 4th June 2020, and 3 prior environmental studies were considered when reviewing this application. She recalled that on 19th November 2020, the developers sought a 6-month extension for the submission of their final application for planning permission, which was granted on 27th November 2020.
[73] On 28th December 2020, Ms. St. Louis indicated that the developers submitted a revision to the master plan, reducing the building site from 375 acres to 256 acres to provide a buffer zone between the development and the RAMSAR site. There was also a proposed 50 percent reduction in the number of villas along with the relocation of the proposed golf course. Ms. St. Louis confirmed that a revised approval in principle was granted on 28th December 2020 in relation to the revisions to the master plan. She also highlighted that a separate EIA was done in relation to the proposed jetty.
[74] The application for final approval for Range was also submitted to PADA before Ms. St. Louis assumed duties on PADA’s board. Approval was granted subject to several conditions on 27th January 2020. She recalled that in March 2020, PADA’s Board received the EIA Committee’s report on the EIA. Ms. St. Louis was of the view that the EIA report was a good report, but opined that it lacked a social component. Around that time, she highlighted that the developer had begun clearing the site without proper approval.