Responses to questions asked by the Leader of His Majesty’s Opposition in the House of Parliament to Prime Minister Dickon Mitchell

Opposition Leader Dr Keith Mitchell

Western Main Road Project

What is the new financing timeline and the new estimated cost of the project?

Answer: There is no new financing timeline and no new estimated cost of the project. The Caribbean Development Bank (CDB) has advised that the financing provided by the United Kingdom CIF is no longer available. The original cost of the project was USD $52M.

What is the original amount of financing received?

Answer: Grant financing of $1.0M Pounds for Technical Assistance to undertake the 2 designs and $6M USD to finance the construction phase.

What are the names of the delegation that travelled to CDB to renegotiate the financing of the project?

Answer: There was no visit to CDB.

Are there any changes in the plans and designs of the project?

Answer: No.

If yes, what are these changes?

Answer: N/A

Who are the service providers?

Answer: Beston Consulting Limited is the Design Consultant. FDL Consultant Inc. was also retained to provide consultancy services.

Molinere Land Slip

What is the time frame for the completion of the project?

Answer: The project has experienced delays which are attributed to the constant deterioration in existing soil conditions at the site. The estimated timeframe for completion is the first quarter of 2024.

Who are the current consultants?

Answer: Beston Consulting Limited

Who are the current service providers?

Answer: Construction & Industrial Equipment Limited is the Contractor

Have new surveys been conducted?

Answer: Yes, to examine the extent of the deterioration that has occurred and continued to occur. The Bureau of Standards has performed several probes of the soil in the area to ascertain any degradation to the piles in place from the original design, as well as inform the revised design solution.

Are there any changes of the plans and designs of the project?

Answer: Changes are currently needed to adjust to the existing ground conditions have deteriorated.
Design modifications are being prepared.

Related:  Russian oilmen sacked

If yes, what are these changes?

Answer: The movement of the material at the upper slope has required the upper bank to be stabilized. This will be done via a geomembrane that will be placed on the surface that will reduce the impact of the elements, as well as provide support to the soil. To re-establish the roadway, additional piling will be done to create a stable foundation for the elevated road deck which will be supported by a reinforced concrete structure. This will negate the effects of any debris that may potentially have an impact on the proper functioning of the road after it is reopened. Also, works to stabilize the area downslope of the road will take place with a similar solution to that of the upslope.

St. John’s River Project

What is the completion date of the project?

Packages 1 & 2 ( Creative Design) 30th April 2023

Packages 3 & 4 (KeeChanona / Sonrise) 1st September 2022

b) What Changes have been made to the project?

Packages 1 & 2 ( Creative Design)

  • Additional Slope Stabilisation
  • Temporary Buildings for Vendors
  • Installation of Flap gates and safety Ladders
  • Installation of Rip Rap Wall to protect banks
  • Additional Gabion Baskets
  • Extension of Culvert

Packages 3 & 4 (KeeChanona / Sonrise)

  • Toe Beam Protection
  • Drainage to Reinforced Concrete Wall
  • Construction of additional retaining wall and box culvert
  • Remedying of undermined foundation at back of Purcell building

What are the plans for the replacement of the humpback bridge?

Answer: The new design will see the construction of a dual carriageway, reinforced concrete bridge, with pedestrian walkways. Works to complete the remaining river walls will also be completed as part of this package. Works to River Road will be done in a subsequent package.

Are there any cost overruns?

Packages 1 & 2 ( Creative Design) – None

Packages 3 &4 (Kee- Chanona / Sonrise) – None

If yes what are the levels of overruns?

Answer: N/A